How to apply for a commercial electricity connection?

Completion or occupancy certificate from the local authority is required to apply for commercial electricity connection.

Additionally, one has to provide documents proving the ownership or occupation, along with attested copies of the documents showing the proposed location of the meter board. An agreement should also be made on Rs.50 stamp paper.

The application for commercial electricity connection should be filled at the nearest BESCOM sub-divisional office, and remit the required registration fee. The power installation will be serviced within a month from the date of receipt of the licensed contractor's report.

For details, contact: 080 22341199 or log on to www.bescom.org/en/services